South Carolina Electric and Gas Co slugging customers for costs of nuclear reactors that might never be built
Power surge: Cost overruns at South Carolina nuclear plant growing part of SCE&G customer bills, Post and Courier David Wren Email @David_Wren_ 19 June 16 The state legislation allowing South Carolina Electric & Gas Co. to charge customers for two new reactors at its nuclear power plant years before they are completed has been compared to making payments on a new car without knowing the final price and before it leaves the assembly line.
The monthly payments continue to rise, but it’s not certain whether the customer making those payments will ever drive the car.
At least now, SCE&G’s customers have an idea how much the expansoin of the V.C. Summer Nuclear Station is costing them each month. The state’s Office of Regulatory Staff, which represents the public’s interest in utility issues, this month said SCE&G’s customers are paying an average of $23.16 each billing period — or 16.1 percent of their total bill — toward building the Midlands nuclear plant
And that’s likely to increase if the state Public Service Commission approves the company’s request to boost the project’s cost by another $852 million to $14 billion — more than $4 billion higher than original cost estimates.
SCE&G is using a state law called the Base Load Review Act to finance the nuclear project near Jenkinsville.
The law allows the utility to charge its 700,000 customers for construction as the project proceeds. ……
Critics like Frank Knapp, president and CEO of the state’s Small Business Chamber of Commerce, say the act “has turned into a blank check” for SCE&G.
The utility is allowed by state regulators to take up to 10.5 percent of the construction costs as profit. And Knapp says the pay-as-you-go method is unfair because some customers now paying for the project will leave the utility’s service area before it comes online……. http://www.postandcourier.com/20160618/160619424/power-surge-cost-overruns-at-south-carolina-nuclear-plant-growing-part-of-sceg-customer-bills
No comments yet.
-
Archives
- December 2025 (236)
- November 2025 (359)
- October 2025 (377)
- September 2025 (258)
- August 2025 (319)
- July 2025 (230)
- June 2025 (348)
- May 2025 (261)
- April 2025 (305)
- March 2025 (319)
- February 2025 (234)
- January 2025 (250)
-
Categories
- 1
- 1 NUCLEAR ISSUES
- business and costs
- climate change
- culture and arts
- ENERGY
- environment
- health
- history
- indigenous issues
- Legal
- marketing of nuclear
- media
- opposition to nuclear
- PERSONAL STORIES
- politics
- politics international
- Religion and ethics
- safety
- secrets,lies and civil liberties
- spinbuster
- technology
- Uranium
- wastes
- weapons and war
- Women
- 2 WORLD
- ACTION
- AFRICA
- Atrocities
- AUSTRALIA
- Christina's notes
- Christina's themes
- culture and arts
- Events
- Fuk 2022
- Fuk 2023
- Fukushima 2017
- Fukushima 2018
- fukushima 2019
- Fukushima 2020
- Fukushima 2021
- general
- global warming
- Humour (God we need it)
- Nuclear
- RARE EARTHS
- Reference
- resources – print
- Resources -audiovicual
- Weekly Newsletter
- World
- World Nuclear
- YouTube
-
RSS
Entries RSS
Comments RSS


Leave a comment