$47 billion and counting – the cost of nuclear safety upgrades, post Fukushima

Money down holeNuclear safety upgrades post-Fukushima cost $47 billion, The Barrel, Platt’s, 20 Mar 16 Five years after the accident at Fukushima I in Japan resulted in three reactor meltdowns, the global nuclear industry is spending $47 billion on safety enhancements mandated after the accident revealed weaknesses in plant protection from earthquakes and flooding. This is according to a Platts review put together by Steven Dolley in DC, Benjamin Leveau in London, Yuzo Yamaguchi from Tokyo, as well as Platts correspondents in Sweden, South Korea and China.

Reactions to the March 11, 2011 accident ranged from pauses in new nuclear construction programs in China to Germany’s decision to gradually phase out nuclear generation.

But in the majority of countries with nuclear power, plans for new reactors have been scaled back, not just because of the Fukushima I accident but for economic reasons, as competing sources of power become less expensive, renewable energy grows in popularity and slow economic growth curbs demand.

Global nuclear regulators carried out reviews of the accident, and in most countries nuclear plant operators were required to install backup sources of electric power and cooling water along with additional protection from earthquakes and flooding. A record-setting earthquake triggered a tsunami that swamped backup emergency power generators and disabled on-site power distribution systems at Fukushima I, leading to a complete loss of cooling.

Those safety improvements have come at a high cost.

A Platts review found that in nine of the 13 countries with the largest nuclear fleets, costs to comply with post-Fukushima requirements will total more than $40 billion, mostly before 2020. Those countries accounted for 289, or two-thirds, of the power reactors in operation worldwide.

The median of the costs was $46.9 million/reactor.

If the remaining reactors not covered in the Platts survey spent the median amount to meet post-Fukushima regulatory requirements, the global cost to make post-Fukushima enhancements would be $47.2 billion. The greatest cost per country was in Japan, where operators may spend $640 million per reactor to enhance safety.

The OECD Nuclear Energy Agency released a five-year status report on the Fukushima I accident, concluding that actions implemented by member countries had improved the overall safety of the world’s nuclear fleet, but that enhancing safety remains “a long-term process.”……..

Anti-nuclear groups have said the regulatory and industry response following the Fukushima I accident has been insufficient. Regulators in the US have “capitulated” to industry by failing to order vent filters, the group Beyond Nuclear said in a March 10 statement.

Measures to protect nuclear plants from earthquakes and flooding have left unaddressed vulnerabilities in areas such as plant security, the group said.

The biggest problem facing US nuclear plant operators recently has been economic. Low natural gas prices and an abundance of cheap renewable electricity in some markets have created financial problems for nuclear plants in competitive electricity markets. Entergy in late 2015 said it would permanently shut two stations, the 849 MW FitzPatrick in New York state and 728 MW Pilgrim in Massachusetts.

Japan’s nuclear reactors were all shut following the Fukushima I accident, and only two have met regulatory requirements and restarted.

The country’s nuclear industry has budgeted about Yen 3.1 trillion ($27.5 billion) for earthquake and tsunami protection following the accident………http://blogs.platts.com/2016/03/29/nuclear-safety-upgrades-post-fukushima/

March 30, 2016 - Posted by | business and costs, safety