UK’s Sellafield clean-up mess: Amec, Areva and URS stripped of £20bn contract

money-in-nuclear--wastesflag-UKSellafield nuclear clean-up firms to be stripped of £20bn contract, Telegraph UK  Management of Britain’s most toxic nuclear waste site expected to be taken back into state hands as heavily-criticised consortium of Amec, Areva and URS is stripped of its contract By , Energy Editor 12 Jan 2015 Nuclear waste clean-up operations at Sellafield are expected to be taken back into state hands, as the private consortium managing the Cumbrian site is stripped of its £20bn contract.

The Government’s decision to axe Nuclear Management Partners (NMP), comprised of Britain’s Amec, France’s Areva and America’s URS, is expected to be formally announced on Tuesday, six years into a 17-year contract to work on decommissioning the site.

Ministers surprised many by shying away from an opportunity to cancel NMP’s contract at a formal “break point” last year, despite criticism of the consortium by the National Audit Office (NAO) and Public Accounts Committee (PAC) over a series of failings.

The Nuclear Decommissioning Authority (NDA) had said it was considering taking the management of Sellafield back into state hands, an option that would have required ministerial approval.

However, there were doubts about how state management of the nuclear site, the UK’s biggest and most hazardous, would work in practice. It is thought a plan has now been drawn up and the NDA will exercise its right to terminate NMP’s contract “for convenience” with 12 months’ notice.

A spokesman for the Department of Energy and Climate Change confirmed only that the NDA and Government had been working on “alternative options at Sellafield”……..

the costs of the clean-up have since spiralled and annual spending at the site last year was £1.8bn, implying the remaining 11 years of the contract would be worth £20bn.

NMP earns tens of millions of pounds each year for managing the multi-billion pound operations.

Lifetime costs for decommissioning Sellafield, which is likely to take more than 100 years, were last year estimated to have risen to in excess of £79bn, but the NDA warned at the time that the total would rise further.

The NAO and PAC both criticised delays and cost overruns in NMP’s management Sellafield, where failings also included accidentally sending radioactive waste to a landfill site, resulting in a £700,000 fine………http://www.telegraph.co.uk/finance/newsbysector/energy/11340733/Sellafield-nuclear-clean-up-firms-to-be-stripped-of-20bn-contract.html

January 14, 2015 - Posted by | politics, UK, wastes