Georgia’s new nuclear power plant getting stymied by costs and delays?

nukes-hungryFlag-USAConstruction time uncertain for Ga. nuclear plant Star Telegram, Aug. 28, 2014 BY RAY HENRY Associated Press ATLANTA — Georgia Power said its $6.7 billion budget to build a new nuclear plant is holding steady, but it reported Thursday that builders face “challenges” sticking to the construction schedule and costs could change in the future…….Georgia Power has so far spent $2.8 billion on the project, according to company filings. The other owners, Oglethorpe Power Corp., the Municipal Electric Authority of Georgia and the city of Dalton, do not report their spending to the Public Service Commission.

The latest cost estimates are uncertain. Utility officials and regulators have previously said Georgia Power does not have a schedule from the companies designing and building the plant, Westinghouse Electric Co. and Chicago Bridge & Iron Co., that detail construction activities past the end of 2015.

“The Company expects the Contractor to employ all possible means to meet the current schedule targets; however, schedule pressures continue to challenge the project,” the report said.

Project schedules have slid since the plant was first approved. The first new reactor was supposed to start producing power in April 2016, with the second following a year later. Georgia Power has since pushed that schedule back to late 2017 and late 2018. Delays are bad for the nuclear industry and electric customers. The longer it takes to build a nuclear plant, the more Georgia Power and its co-owners must pay to finance construction and pay for other charges.

Ultimately, customers pay those expenses unless regulators intervene………

Analysts have been watching Georgia Power’s filings for any signs of additional delays or costs. The current budget does not earmark any money for resolving an ongoing lawsuit between the new plant’s owners and the firms who are designing and building it…….http://www.star-telegram.com/2014/08/28/6075221/construction-time-uncertain-for.html