nuclear-news

The News That Matters about the Nuclear Industry Fukushima Chernobyl Mayak Three Mile Island Atomic Testing Radiation Isotope

Radiation situation at Fukushima is unimaginably bad

FUKUSHIMA-2013No workers were visible around the No. 3 reactor building. An unmanned crane was removing debris on the roof.


It is hazardous to human health to work in the reactor building where
radiation levels range from 20 to 100 millisieverts per hour.

water-radiationThe amount of radioactive water stored in tanks and other facilities
rose to 230,000 tons this month, up from 10,000 tons in July 2011.

In addition, an estimated 100,000 tons of water have accumulated in
the basements of buildings.

Decommissioning will not be completed for the next 30 to 40 years

High radiation bars decommissioning of Fukushima plant Asahi highly-recommendedShimbun,
February 21, 2013
By HISASHI HATTORI/ Senior Staff Writer
Preparations for the mammoth task of decommissioning crippled reactors
at the Fukushima No. 1 nuclear power plant are being stymied by
continued high levels of radiation from the triple meltdowns there two
years ago.

Tokyo Electric Power Co., operator of the plant, has had to install
more tanks to store radioactive water, which continues to swell by
several hundreds of tons daily.
water tanks Fukushma
Asahi Shimbun reporters entered the No. 4 reactor building on Feb. 20,
accompanied by inspectors from the secretariat of the Nuclear
Regulation Authority, to assess the situation…..

Most of the debris, such as steel frames mangled in the explosion,
have been removed from the roofless top floor of the reactor building,
but radiation levels remain high.

“Here, the reading is 200 microsieverts per hour,” an inspector said.
“But it is 1,000 microsieverts on the north side close to the No. 3
reactor building. Keep your distance.”

A shroud has been placed over the spent fuel storage pool on the top
floor. The water temperature was about 20 degrees. The water, seen
through an opening, was muddy and brown. The fuel inside the pool was
not visible.

Workers were installing a shroud for the No. 4 reactor building on the
south side of the building. It will be equipped with a crane to remove
spent fuel from the storage pool.

The foundation work was already completed, and steel frames were being
assembled.

TEPCO intends to mount a determined effort to remove spent fuel from
the storage pool in November. Two fuel assemblies were removed on a
trial basis in July….

From the top floor of the No. 4 reactor building, the No. 3 reactor
building resembled a bird’s nest made of twisted steel frames.

No workers were visible around the No. 3 reactor building. An unmanned
crane was removing debris on the roof.

It is hazardous to human health to work in the reactor building where
radiation levels range from 20 to 100 millisieverts per hour.

The No. 1 and No. 2 reactors also went in meltdown. Asahi Shimbun
reporters got close to the two reactor buildings by taking routes
where radiation levels are relatively low.

Still, the dosimeter reading was 700 microsieverts per hour east of
the No. 2 reactor turbine building.

The cumulative radiation dose was 0.111 millisievert after the
approximately four-hour tour of the Fukushima No. 1 plant…….

“We have yet to identify all hotspots, where radiation levels are
locally high,” Kosaka said.

Ever-increasing radioactive water has become a key challenge for TEPCO.

Groundwater is flowing into reactor buildings, where it mixes with
water used to cool melted fuel inside the No. 1, No. 2 and No. 3
reactors.

The amount of radioactive water stored in tanks and other facilities
rose to 230,000 tons this month, up from 10,000 tons in July 2011.

In addition, an estimated 100,000 tons of water have accumulated in
the basements of buildings.

Currently, there are nearly 500 storage tanks on the plant premises,
many as tall as three-story buildings. TEPCO plans to add more by 2015
when it expects to have to store 700,000 tons of radioactive water.

Inside a radioactive water decontamination facility called Sarry,
cylindrical cesium adsorption towers were lined up.

Cesium concentrations in radioactive water have recently fallen, but
an inspector kept reporters from approaching the towers, saying
radiation levels are high……

Preparations for decommissioning have only recently begun.
Decommissioning will not be completed for the next 30 to 40 years
under a plan drawn up by the government and TEPCO.

Trial and error is the only way available because the triple meltdowns
are unprecedented…….

Currently, workers cannot easily approach the three reactor buildings
where the meltdowns occurred due to high radiation levels. They have
been removing debris, such as concrete blocks, on the plant premises.

Work to remove melted fuel from the three reactors is expected to
begin by around 2022. Fuel is believed to be scattered within the
pressure vessels, containment vessels or piping systems, but exact
locations remain unclear.

In addition, TEPCO has yet to identify where radioactive water has
been leaking from the damaged containment vessels. The containment
vessels must be filled with water before melted fuel is removed.

In December, TEPCO sent a remote-controlled robot near the pressure
suppression chamber in the No. 2 reactor building to find out where
water was leaking. But the mission failed when the robot lost its
balance and got stuck.

New technologies must be developed for decommissioning, but
manufacturers and general contractors have shown little enthusiasm.

The companies fear they will not be able to recover their investments
because the technologies would have little practical application other
than for the Fukushima plant…..
http://ajw.asahi.com/article/0311disaster/fukushima/AJ201302210064

February 22, 2013 - Posted by | Fukushima 2013, Japan, radiation, Reference

1 Comment »

  1. Are the water storage tanks earthquake-tsunami hardened?

    ttmallard's avatar Comment by ttmallard | July 8, 2013 | Reply


Leave a comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.