Finland -Olkiluoto 3’s new-generation reactor hits more delays, casting an ill light on its viability
Charles Digges, 12/02-2013
http://www.bellona.org/articles/articles_2013/Olkiluoto_more_delays
The troubled Olkiluoto 3 nuclear plant in Finland “is preparing for the possibility” that it will not start operating before 2016, the power utility behind the plant said Monday, adding another delay to a project that is already four years overdue.
The announcement sheds a dim light on the practicality and expense of the first-of-its kind new-generation European Pressurized reactor, which has been touted as a revolution in nuclear power production.
“This is yet another blow to the supposed nuclear renaissance,” said Bellona General Manager and nuclear physicist Nils Bøhmer. “Costly delays and millions of euro in price overruns are completely impractical, especially when compared to pursuing cheaper renewable and alternative energy sources.”
Teollisuuden Voima, (TVO), the Finnish utility for which the EPR is being built, said recent progress reports received from the plant supplier, the Areva-Siemens consortium, suggest that earlier forecasts of a 2014 start were unlikely to be met.
The delay is just one of a series of setbacks over the past years.
In May 2005, when work started on the reactor – which is currently slated to cost about €2.5 billion – its completion was scheduled for 2009. TVO announced in December 2011 that it anticipated the 1600 MWe plant to begin commercial operation in August 2014, some five years later than originally planned.
In July 2012, the company declared that the plant unit “will not be ready for regular electricity production in 2014.”
Noting that Areva-Siemens are constructing the 1600 MWe plant under a fixed-price turnkey contract and are therefore responsible for the time schedule of the project, it requested the supplier provide an updated schedule and completion date, World Nuclear News reported.
The giant facility, which is under construction on an island in the Baltic Sea, is forecasted to be large enough to supply 10 percent of Finland’s electricity needs.
Tit for tat statements from TVO and Areva Siemens
TVO’s senior vice president of the Olkiluoto 3 project, Jouni Silvennoinen, said in a statement Monday, “We have not yet received an adequate schedule update.”
Silvennoinen added that failure to gain timely regulatory approval for the reactor’s digital instrumentation and control equipment has also delayed the start of operations.
According to the International Atomic Energy Agency (IAEA), the so-called “I&C equipment” is “the nervous system” of a nuclear facility, providing operators with a way to monitor operations and respond to developments.
Cost overruns remain unknown
Silvennoinen declined to comment to news agencies on what the final cost of the plant was likely to be or how much it was now over budget, given the chain of delays.
TVO said it had asked the consortium “to update the overall schedule and provide a new confirmation for the completion date,” adding that although it “is not pleased with the situation and repeated challenges with the project scheduling,” work is proceeding at the unit.
TVO further stated that it continues to provide support to the Areva-Siemens consortium “to complete the project as soon as possible.”
Areva-Siemens and TVO at loggerheads in arbitration
The battle between TVO and Areva-Siemens –who will bear responsibility for cost overruns, is in arbitration at the International Chamber of Commerce, Reuters reported.
The Areva-Siemens consortium fired back, saying in a statement that both the French and British nuclear safety authorities had already largely signed off on the equipment, blaming TVO for the delays.
“Over the course of the past year, the consortium has asked for significantly more active cooperation from TVO in order to obtain the final approval of the detailed I&C architecture,” the statement read. “The Areva-Siemens consortium regrets that TVO continues to not fulfill its obligations to allow for the project to advance properly.”
Untested reactor design
Should it reach completion, the Olkiluoto plant, employing the new-generation EPR would be among the most powerful nuclear facilities ever built. A second EPR. plant, under construction in Flamanville, France for EDF is also significantly over budget.
There are, as yet, no examples of the new reactor type working anywhere in the world, but there are two more such plants under construction in China, at a site in Taishan, Guangdong Province.
The Areva-Siemens consortium said Monday that construction at Taishan “is advancing twice as fast as the Finnish project,” the New York Times reported.
Nuclear self-sufficiency for Finland?
TVO’s announcement of a further potential delay in the Olkiluoto 3 project comes just days after the Finnish government published an updated strategy for meeting its energy and climate change targets, WNN reported.
In its climate change plan, Finland’s Ministry of Employment and the Economy also argues that the country is still not self sufficient in electricity generation and depends too heavily on imports during its frigid winters – a situation it says will remain until the Olkiluoto 3 plant starts operation.
Bellona has long opposed the use of nuclear power to meet worldwide emissions reduction as dangerous, time consuming and exorbitantly costly – as evidenced by the Olkiluoto3 project – when compared to renewable and alternative energy sources. It also compounds the fact that no safe method has yet been found for dealing long-term with spent nuclear fuel and radioactive waste with immense climate challenges that are already in evidence. The organization also says that by the time new generation nuclear power plants are built – given an average 10-year construction period for any given nuclear power plant – the benefits of CO2-free energy production will have been overtaken by the worst of what climate change has in store.
http://www.bellona.org/articles/articles_2013/Olkiluoto_more_delays
No comments yet.
-
Archives
- December 2025 (213)
- November 2025 (359)
- October 2025 (377)
- September 2025 (258)
- August 2025 (319)
- July 2025 (230)
- June 2025 (348)
- May 2025 (261)
- April 2025 (305)
- March 2025 (319)
- February 2025 (234)
- January 2025 (250)
-
Categories
- 1
- 1 NUCLEAR ISSUES
- business and costs
- climate change
- culture and arts
- ENERGY
- environment
- health
- history
- indigenous issues
- Legal
- marketing of nuclear
- media
- opposition to nuclear
- PERSONAL STORIES
- politics
- politics international
- Religion and ethics
- safety
- secrets,lies and civil liberties
- spinbuster
- technology
- Uranium
- wastes
- weapons and war
- Women
- 2 WORLD
- ACTION
- AFRICA
- Atrocities
- AUSTRALIA
- Christina's notes
- Christina's themes
- culture and arts
- Events
- Fuk 2022
- Fuk 2023
- Fukushima 2017
- Fukushima 2018
- fukushima 2019
- Fukushima 2020
- Fukushima 2021
- general
- global warming
- Humour (God we need it)
- Nuclear
- RARE EARTHS
- Reference
- resources – print
- Resources -audiovicual
- Weekly Newsletter
- World
- World Nuclear
- YouTube
-
RSS
Entries RSS
Comments RSS



Leave a comment