Sellafield nuclear waste storage poses ‘intolerable risk’ -Hitachi to burn plutonium
“It also concluded that over the five decades it was open, operators failed to plan how to dispose of the radioactive waste and some of the older facilities have “deteriorated so much that their contents pose significant risks to people and the environment”.”
Sellafield audit shows safety costs spiralling
- Rajeev Syal and Fiona Harvey
- guardian.co.uk, Wednesday 7 November 2012
The projected cost of safely storing radioactive material at Britain’s largest nuclear site in Sellafield has increased by more than £900m in 10 months, the National Audit Office says in a report released on Wednesday.
Plans to replace the ageing nuclear waste facilities in Cumbria have suffered severe delays, auditors said. Twelve out of 14 of the major projects launched last year to build facilities to store material safely are over budget, they have concluded.
The findings have been described as “dire” by MPs. It is the first official audit of the Cumbrian site since a consortium of private companies was brought in to oversee safety in 2008.
Margaret Hodge, who chairs parliament’s public accounts committee, urged the Nuclear Decommissioning Authority (NDA) to “get a grip” on the spiralling costs. “My concern is that unless the authority holds Sellafield Limited [the company responsible for the site] to a clear and rigorously benchmarked plan, timetables will continue to slip and costs spiral.
“It is totally unacceptable to allow today’s poor management to shift the burden and expense of Sellafield to future generations of taxpayers and their families,” she said.
In 2008, the authority appointed a consortium of private sector companies – URS, AMEC and Areva – as a parent body of the site to bring in outside expertise. The authority plans to clear up the site over the next 108 years.
[…]
A long-term plan to clean up the site, which is managed by Sellafield Limited, was agreed last year after an earlier one stalled because it was “unrealistic”.
Sellafield, the UK’s most hazardous nuclear site, stores enough high and intermediate level radioactive waste to fill 27 Olympic-sized swimming pools.
For more than 50 years operators failed to plan how to dispose of the radioactive waste and some of the older facilities have “deteriorated so much that their contents pose significant risks to people and the environment”, the report said. The highest risks are posed by ponds and silos built during the 1950s and 1960s to store fuel for early reprocessing operations and radioactive waste, according to the report.
[…]
The management of the authority and Sellafield have often been criticised for being a closed group of insiders insufficiently transparent to outside scrutiny. Critics say this has led to a culture where poor decision-making has been tolerated.
Next year, a major industry shake-up could occur as the authority will have to make a decision on whether to review or renegotiate the Sellafield safety contract.
http://www.guardian.co.uk/environment/2012/nov/07/sellafield-audit-safety-costs-spiralling
BBC
7 November 2012 Last updated at 00:14
[…]
An “intolerable risk” is being posed by hazardous waste stored in run-down buildings at Sellafield nuclear plant, a watchdog has found.
The National Audit Office (NAO) also said that for 50 years, the operators of the Cumbria installation failed to develop a long-term plan for waste.
Costs of plant-decommissioning has also spiralled out of control, it said.
[..]
The plant is the UK’s largest and most hazardous nuclear site, storing enough high and intermediate level radioactive waste to fill 27 Olympic-sized swimming pools.
[..]
A long-term plan to clean up the Nuclear Decommissioning Authority-owned site, was agreed last year after an earlier one stalled because it was “unrealistic”.
Margaret Hodge, who chairs the public accounts committee, said: “Projects of this length and ambition are ripe for dithering and delay.
[…]
The authority’s revised plan sees critical milestones shunted back by up to seven years.
[…]
It is totally unacceptable to allow today’s poor management to shift the burden and expense of Sellafield to future generations of taxpayers and their families.”
‘Historic neglect’
The NAO report concludes that progress in 12 of the 14 major buildings and equipment projects considered “critical” for reducing risk, which range in cost from £21m to £1.3bn, also failed to achieve what they were supposed to and had not provided good value for money, the NAO also concluded.
[…]
Around 240 of Sellafield’s 1,400 buildings are nuclear facilities and so far 55 buildings on the site have been decommissioned.
http://www.bbc.co.uk/news/uk-england-cumbria-20228176
Nuclear waste to burn at Sellafield?
GE Hitachi is poised to hand nuclear authorities a report that the US-Japanese joint venture believes will prove that Britain can solve its 100-tonne plutonium waste problem by burning it.
The UK’s stockpile is the biggest civil waste deposit in the world, and the Nuclear Decommissioning Authority (NDA), which is responsible for cleaning it up, had planned to convert the plutonium into fuel for other reactors.
However, GE Hitachi will say in a feasibility study to be handed to the NDA in the next two weeks that its Prism fast-reactor design could eliminate the waste, with the bonus of producing low-carbon electricity. The group wants to build a plant at Sellafield in Cumbria, and has agreed to submit a study to the NDA, which has previously been sceptical over fast-reactor technology.
http://www.independent.co.uk/news/business/news/nuclear-waste-to-burn-at-sellafield-7901669.html
3 Comments »
Leave a comment
-
Archives
- December 2025 (293)
- November 2025 (359)
- October 2025 (377)
- September 2025 (258)
- August 2025 (319)
- July 2025 (230)
- June 2025 (348)
- May 2025 (261)
- April 2025 (305)
- March 2025 (319)
- February 2025 (234)
- January 2025 (250)
-
Categories
- 1
- 1 NUCLEAR ISSUES
- business and costs
- climate change
- culture and arts
- ENERGY
- environment
- health
- history
- indigenous issues
- Legal
- marketing of nuclear
- media
- opposition to nuclear
- PERSONAL STORIES
- politics
- politics international
- Religion and ethics
- safety
- secrets,lies and civil liberties
- spinbuster
- technology
- Uranium
- wastes
- weapons and war
- Women
- 2 WORLD
- ACTION
- AFRICA
- Atrocities
- AUSTRALIA
- Christina's notes
- Christina's themes
- culture and arts
- Events
- Fuk 2022
- Fuk 2023
- Fukushima 2017
- Fukushima 2018
- fukushima 2019
- Fukushima 2020
- Fukushima 2021
- general
- global warming
- Humour (God we need it)
- Nuclear
- RARE EARTHS
- Reference
- resources – print
- Resources -audiovicual
- Weekly Newsletter
- World
- World Nuclear
- YouTube
-
RSS
Entries RSS
Comments RSS


It is utterly astounding to me that this filthy dirty murdering industry has been able to keep all of its secret poison deeds so disguised as PEACEFUL nuclear. There is no such thing. We have made a TRAGIC mistake and we need to stop making it and ISOLATE the waste- immediately. Shut every single operating reactor down and ISOLATE the poison… or it WILL be the end of mankind- at least mankind as we know him… some other sick, diseased, mutant mankind may survive it… for a time… but not OUR kind… our kind will perish in the flames of the nuclear fire that burns forever…
Reblogged this on nuclearwindsatomiclies and commented:
It is utterly astounding to me that this filthy dirty murdering industry has been able to keep all of its secret poison deeds so disguised as PEACEFUL nuclear. There is no such thing. We have made a TRAGIC mistake and we need to stop making it and ISOLATE the waste- immediately. Shut every single operating reactor down and ISOLATE the poison… or it WILL be the end of mankind- at least mankind as we know him… some other sick, diseased, mutant mankind may survive it… for a time… but not OUR kind… our kind will perish in the flames of the nuclear fire that burns forever…
Reblogged this on Fukushima Archives and commented:
It is utterly astounding to me that this filthy dirty murdering industry has been able to keep all of its secret poison deeds so disguised as PEACEFUL nuclear. There is no such thing. We have made a TRAGIC mistake and we need to stop making it and ISOLATE the waste- immediately. Shut every single operating reactor down and ISOLATE the poison… or it WILL be the end of mankind- at least mankind as we know him… some other sick, diseased, mutant mankind may survive it… for a time… but not OUR kind… our kind will perish in the flames of the nuclear fire that burns forever…