New plutonium nuclear fuel plant, costly, delayed, and unsafe, too?
More than a decade later, the mixed oxide fuel [2] (MOX) plant is running into mounting troubles [3], including long delays, soaring costs and the lack of utilities committed to use the new fuel in their reactors
But there’s another aspect of the story that has received little attention…

Safety Reviewers Raise Questions about Construction of New Nuclear Fuel Plant, ProPublica By Donna Deedy, w ith Michael Grabell, May 5, 2011, . In the late 1990s, U.S. policymakers approved a plan to turn plutonium from nuclear weapons into fuel for commercial reactors. The first-of-its kind plant [1], now being built in South Carolina, was intended to reduce the Cold War stockpile and the threat of nuclear material theft while supplying the country’s energy needs.
More than a decade later, the mixed oxide fuel [2] (MOX) plant is running into mounting troubles [3], including long delays, soaring costs and the lack of utilities committed to use the new fuel in their reactors
But there’s another aspect of the story that has received little attention. Two of the Nuclear Regulatory Commission’s safety reviewers for the project say the NRC has taken shortcuts on safety to avoid delaying the construction. Work on the facility was allowed to begin, they say, before some of the most essential questions were fully answered. They have been particularly concerned about the danger of chemical explosions, the adequacy of the ventilation and radioactive waste disposal systems and the way the plutonium will be tracked as it is processed.
Alex Murray, the lead chemical process engineer on the NRC review team, has said in public documents [4] that he was removed from the project in 2007, after he repeatedly warned that safety plans to prevent a chemical explosion risk specific to this type of plant were inadequate and could lead to a significant release of radioactive material.
After Murray was reassigned, the NRC hired Dan Tedder, a chemical engineering professor from the Georgia Institute of Technology who had participated in technical reviews for the Department of Energy since 1979. Tedder said he resigned less than a year later because he believed that the plant’s chemical engineering plans were incomplete and felt that his concerns were brushed aside……..
The MOX plant is the first new construction authorized by the NRC since the Three Mile Island accident [6] in 1979. It is located at the federal Savannah River Site [7], an old bomb-making complex near Aiken, S.C. Originally estimated at $1.4 billion, it is now expected to cost taxpayers [8] nearly $5 billion. It won’t begin producing fuel until 2016 at the earliest, about a decade behind schedule.
Areva Inc. CEO Jacques Besnainou criticized the news media for sensationalizing the dangers of MOX, saying the fuel is safe and has been rigorously tested. He said the company values transparency and encouraged readers to “learn the facts of this issue.” But Areva declined to answer ProPublica’s questions about the plant, as did Shaw and a spokesman for their partnership. Instead, they referred questions to the U.S. Department of Energy, which declined requests to interview officials in charge of the program……
The NRC’s jurisdiction, Dan Tedder noted, is narrow. The agency regulates hazardous chemicals produced from radioactive materials. But it does not identify and protect against all chemical hazards.
For instance, the chemical mixing and storage building that adjoins the MOX plant is regulated by the U.S. Occupational Safety and Health Administration. The NRC says it’s responsible for any event that could affect the MOX plant, but safety reviewers said that dual setup could leave workers vulnerable if an accident occurred.
He said it’s also unclear how all the radioactive waste from the plant will be tracked and stored. Waste issues fall under the jurisdiction of the Energy Department, which is building a new plant where liquid waste will be treated, mixed into cement and packed into 55-gallon drums. But it has not been decided yet where the waste will ultimately be disposed of…..
“We need congressional hearings on this,” Tedder said. “The NRC review of MOX is not comprehensive. As a professional engineer, I find this position unacceptable and inconsistent with accepted engineering practices.”
.Safety Reviewers Raise Questions about Construction of New Nuclear Fuel Plant – ProPublica
No comments yet.
-
Archives
- December 2025 (301)
- November 2025 (359)
- October 2025 (377)
- September 2025 (258)
- August 2025 (319)
- July 2025 (230)
- June 2025 (348)
- May 2025 (261)
- April 2025 (305)
- March 2025 (319)
- February 2025 (234)
- January 2025 (250)
-
Categories
- 1
- 1 NUCLEAR ISSUES
- business and costs
- climate change
- culture and arts
- ENERGY
- environment
- health
- history
- indigenous issues
- Legal
- marketing of nuclear
- media
- opposition to nuclear
- PERSONAL STORIES
- politics
- politics international
- Religion and ethics
- safety
- secrets,lies and civil liberties
- spinbuster
- technology
- Uranium
- wastes
- weapons and war
- Women
- 2 WORLD
- ACTION
- AFRICA
- Atrocities
- AUSTRALIA
- Christina's notes
- Christina's themes
- culture and arts
- Events
- Fuk 2022
- Fuk 2023
- Fukushima 2017
- Fukushima 2018
- fukushima 2019
- Fukushima 2020
- Fukushima 2021
- general
- global warming
- Humour (God we need it)
- Nuclear
- RARE EARTHS
- Reference
- resources – print
- Resources -audiovicual
- Weekly Newsletter
- World
- World Nuclear
- YouTube
-
RSS
Entries RSS
Comments RSS


Leave a comment