Way behind schedule – UK’s planned nuclear reactors
the companies behind the designs – French consortium Areva, EDF and US firm Westinghouse – had been repeatedly submitting information which was incomplete and late………we could be faced with the farcical situation where the government is letting utilities press ahead with building work for reactors that haven’t been given safety approval.”
UK’s nuclear reactor programme falls behind schedule. Regulator and builders blame each other for construction hold-up as designs await approval Tim Webb , guardian.co.uk, , 25 August 2010 The schedule for the UK’s nuclear reactor building programme has slipped behind already, the safety regulator has admitted, reinforcing concerns that the first reactor will not be built on time.
The Health and Safety Executive (HSE) said it would probably have to issue an “interim” decision on the safety of the two new proposed reactor designs next June, the deadline for its assessment programme. The regulator expects significant chunks of extra work will remain before it can finally approve or reject the designs, but did not say how long this would take.
Kevin Allars, director of the assessment programme at the HSE, said that companies could continue planning and carry out preparatory construction on proposed nuclear sites while they waited for a final decision. But he insisted that construction of a reactor could not start without its consent.
Allars promised there would be no repeat of the chaotic construction in Finland of what was supposed to be Europe’s first new reactor in decades. The Areva plant is more than three years behind schedule and more than €2bn (£1.6bn) over budget, with the Finnish regulator trying to approve each component of the design while it is being built. EDF has promised that the UK’s first reactor will be operational in 2018, although it had originally said it would be running by the end of 2017.
The HSE said the companies behind the designs – French consortium Areva, EDF and US firm Westinghouse – had been repeatedly submitting information which was incomplete and late………
A Greenpeace spokesman said: “The generic design assessment [GDA] process has already unearthed a string of nasty surprises within the new nuclear reactors’ designs. But now we find out GDA won’t even be able to give a final green light to the reactor designs. This means we could be faced with the farcical situation where the government is letting utilities press ahead with building work for reactors that haven’t been given safety approval.”
No comments yet.
-
Archives
- December 2025 (223)
- November 2025 (359)
- October 2025 (377)
- September 2025 (258)
- August 2025 (319)
- July 2025 (230)
- June 2025 (348)
- May 2025 (261)
- April 2025 (305)
- March 2025 (319)
- February 2025 (234)
- January 2025 (250)
-
Categories
- 1
- 1 NUCLEAR ISSUES
- business and costs
- climate change
- culture and arts
- ENERGY
- environment
- health
- history
- indigenous issues
- Legal
- marketing of nuclear
- media
- opposition to nuclear
- PERSONAL STORIES
- politics
- politics international
- Religion and ethics
- safety
- secrets,lies and civil liberties
- spinbuster
- technology
- Uranium
- wastes
- weapons and war
- Women
- 2 WORLD
- ACTION
- AFRICA
- Atrocities
- AUSTRALIA
- Christina's notes
- Christina's themes
- culture and arts
- Events
- Fuk 2022
- Fuk 2023
- Fukushima 2017
- Fukushima 2018
- fukushima 2019
- Fukushima 2020
- Fukushima 2021
- general
- global warming
- Humour (God we need it)
- Nuclear
- RARE EARTHS
- Reference
- resources – print
- Resources -audiovicual
- Weekly Newsletter
- World
- World Nuclear
- YouTube
-
RSS
Entries RSS
Comments RSS



Leave a comment