Costly delays in fixing nuclear plant

nuclear-costsPoint Lepreau refurbishment 9 months late
September 2, 2009  ATCBC News

The troubled $1.4-billion refurbishment of the Point Lepreau nuclear reactor is suffering another setback, pushing the massive project nine months behind schedule, CBC News has learned.

Sources inside NB Power say the refurbishment of the reactor is being stalled because of problems with the installation of the plant’s new calandria tubes…………

Point Lepreau is the first Candu-6 reactor to undergo a complete gutting and rebuild. It was intended to be a showcase for AECL to display its ability to revive the 1980s-era reactors.

When the refurbishment project started, it was supposed to last 18 months and have the reactor back on line in October 2010

However, crews at Point Lepreau struggled to deconstruct the old reactor, finally finishing that stage in late July, almost eight months behind schedule.

NB Power has acknowledged delays at Point Lepreau will cost $20 million a month.

Point Lepreau refurbishment 9 months late