Chris Goodall on the rising costs of UK nuclear energy | Environment | guardian.co.uk
The rising costs of UK nuclear energyThe fall in the pound’s value undermines any financial case for nuclear energy, writes Chris Goodall from Carbon Commentary, part of the Guardian Environment Network 6 Jan 09
“……………………………Since the government’s paper, nuclear power has suffered two huge blows. First, the pound has declined in value against the euro. This makes the core components of a nuclear power station more expensive as they are priced in the European currency. Second, the construction of the new nuclear power station in Finland has descended almost into farce as costs have ballooned and progress has slowed. The Finnish power station is much the more advanced of the two new nuclear plants currently under construction in Europe. If Finland is any guide, nuclear power is far more expensive than anybody expected……………………………………….The Finnish debacle
The French nuclear specialist Areva signed a fixed price contract with the Finnish consortium TVO. The value was about €3bn, in addition to the costs that TVO incurred readying the site for construction work and taking the plans through the Finnish approval processes. Areva has since taken several financial provisions in its accounts, reflecting the problems it has faced in completing the work to its initial budget. A provision is a way of recognising that a firm is going to make a future loss on a contract. So, for example, banks make provisions when it is apparent that a loan to a near-bankrupt company is unlikely ever to be repaid.Areva is largely owned by the French state, although some of its shares are held by investment institutions and others. In the Anglo-Saxon world, having private shareholders would oblige the company to state the absolute size of these provisions. In France it is different and Areva has consistently refused to state their actual size. But the French press recently offered the opinion that total provisions may now be €1.5bn, suggesting that Areva thinks that the total cost of fulfilling the contract is already €4.5bn, a rise of 50% on the initial price.
This will not be the end of the matter. Areva has recently indicated that the final completion date of the plant will be sometime in 2012, making the station over three years late. Any further construction problems will raise the total eventual cost yet further……………………………..The value of the euro
If the Finnish construction costs were replicated in the UK, and the euro/pound exchange rate had remained at around £1/€1.50, the cost of the project would imply a cost to generate electricity of over £50 per megawatt hour. This is more than the current wholesale price in the UK (although the wholesale price has been much higher than this figure for most of the last 12 months).
Chris Goodall on the rising costs of UK nuclear energy | Environment | guardian.co.uk
No comments yet.
-
Archives
- December 2025 (301)
- November 2025 (359)
- October 2025 (377)
- September 2025 (258)
- August 2025 (319)
- July 2025 (230)
- June 2025 (348)
- May 2025 (261)
- April 2025 (305)
- March 2025 (319)
- February 2025 (234)
- January 2025 (250)
-
Categories
- 1
- 1 NUCLEAR ISSUES
- business and costs
- climate change
- culture and arts
- ENERGY
- environment
- health
- history
- indigenous issues
- Legal
- marketing of nuclear
- media
- opposition to nuclear
- PERSONAL STORIES
- politics
- politics international
- Religion and ethics
- safety
- secrets,lies and civil liberties
- spinbuster
- technology
- Uranium
- wastes
- weapons and war
- Women
- 2 WORLD
- ACTION
- AFRICA
- Atrocities
- AUSTRALIA
- Christina's notes
- Christina's themes
- culture and arts
- Events
- Fuk 2022
- Fuk 2023
- Fukushima 2017
- Fukushima 2018
- fukushima 2019
- Fukushima 2020
- Fukushima 2021
- general
- global warming
- Humour (God we need it)
- Nuclear
- RARE EARTHS
- Reference
- resources – print
- Resources -audiovicual
- Weekly Newsletter
- World
- World Nuclear
- YouTube
-
RSS
Entries RSS
Comments RSS


Leave a comment